 N4 Hughes Bridge Widening Contract

Traffic on Hughes Bridge is now reduced to a single lane in each direction.  This will inevitably lead to delays of up to 15 minutes during peak times.   

Traffic signals at junction S9 (Hughes Bridge / Ballast Quay / Custom House Quay) will be out of operation for a period of approximately 3 weeks.  During this time the following will apply:

Southbound traffic may continue straight through junction S9 unaffected.

Traffic exiting Custom House Quay and turning left onto the Inner Relief Road must stop and give way to southbound traffic.

 Temporary traffic signals will be in operation for northbound traffic and traffic exiting Ballast Quay.  Every effort will be made to ensure that the timings of the temporary traffic signals are similar to the existing traffic signals timings.

All of the above will be appropriately signed on-site.

 Sligo County Council: As always, we would urge motorists to exercise caution when travelling across Hughes Bridge but most particularly over the coming weeks. 

We thank you for your continued support and patience.

Full details in relation to this bridge widening contract are available on www.sligococo.ie/hughesbridge

 SLIGO-DRUMCLIFF  AREA:

Local Road No. L-3208-0 Carrigeens, Maugherow

Road works will continue on Local Road number L-3208-0 in Carrigeens, Maugherow. Traffic management will be in operation.  Motorists should exercise caution.

TUBBERCURRY  AREA:

Verge trimming works will commence on the N17 Bellahy to Tubbercurry from Monday, 22nd of June. Traffic control will be in operation with major delays expected. Works will last 7 days.

ENNISCRONE  AREA:

Verge improvement works will continue on the N17 at Temple Manor Estate. No delays expected.

Road Restoration will be carried out in Leaffoney.  Traffic management will be in place, minor delays expected.  A 50km/hr speed limit will be in place within the worksite.

Road Restoration will be carried out in Carrowpaddeen.  Traffic management will be in place, minor delays expected.  A 50km/hr speed limit will be in place within the worksite.

BALLYSADARE  AREA:

 N59 in Ballysadare

 Road works will be continuing on the N59 in Ballysadare (between the entrance to Millview Park and theBallina side of the current 60 kph speed limit zone).

Associated traffic delays should be expected over the course of the contract duration.

Sligo County Council and Gerald Love Contracts will endeavour to minimise the effects of the works where possible and regret any inconvenience which may be caused.

MINOR WORKS

 SLIGO CITY AREA:

A Scaffolding licence has been granted for Ulster Bank, Holborn Street.  Works are expected to last 12 weeks.  Some parking spaces will be lost.  Minimal traffic disruption expected.

A Scaffolding licence has been granted for 12 Knappagh Road, Sligo. Works are expected to last 2 weeks. 2 parking spaces will be lost.

 SLIGO /STRANDHILL AREA:

Road repairs will take place in various locations. Minimal traffic disruption expected.

Gully cleaning will take place in various locations. Minimal traffic disruption expected.

BALLYMOTE  AREA:

Road restoration will be carried out on Local Rd. L-1502 at Carrigans Upper.  Traffic management will be in place, minor delays expected.  A 50km/hr speed limit will be in place within the worksite.

Road restoration will be carried out on Local Rd. L-54053 at Bricklieve.  Traffic management will be in place, minor delays expected.  A 50km/hr speed limit will be in place within the worksite.

Surface dressing works will be carried out on Local Rd. L-5801 at Clohogue Upper. Traffic management will be in place, minor delays expected. 

 Surface dressing works will be carried out on Local Rd. L-1502 at Cloonlurg. Traffic management will be in place, minor delays expected.

Road restoration and surface dressing works will be carried out on Local Rd. L-1904 at Barroe Upper/Highwood.  Traffic management will be in place, minor delays expected.  A 50km/hr speed limit will be in place within the worksite.

ENNISCRONE  AREA:

 Pothole repair works will continue in the Enniscrone area. Traffic control will be in operation. Minor delays expected.

 Drainage works will continue in the Enniscrone area. Traffic control will be in operation. Minor delays expected.

Road Restoration will be carried out in MoneraghTraffic management will be in place, minor delays expected.  A 50km/hr speed limit will be in place within the worksite.

Road Restoration will be carried out in ScurmoreTraffic management will be in place, minor delays expected.  A 50km/hr speed limit will be in place within the worksite.

Road Restoration will be carried out in Carrowcaslan/Laragh.  Traffic management will be in place, minor delays expected.  A 50km/hr speed limit will be in place within the worksite.

Road Restoration will be carried out in Ballymurray.  Traffic management will be in place, minor delays expected.  A 50km/hr speed limit will be in place within the worksite.