Sligo County Council Road and Traffic Report

Week commencing 24 August 2015

Sligo News File Online

SCC OfficesMAJOR WORKS

SLIGO AREA:

Site Investigation works are scheduled to take place on Finisklin Road. Traffic Management will be in place and minor delays are expected.  Works are expected to last 1 week.

SLIGO-DRUMCLIFF  AREA:

Road works will take place on Local Road number L-3208-0 in Carrigeens, Maugherow on Monday 24th August.  Works to last two days. Traffic management and diversions will be in operation.  Motorists should exercise caution.

Road works will take place on Local Road number L-3306-0 in Springfield, Rathcormack on Wednesday 26th August.  Works to last one day. Traffic management and diversions will be in operation.  Motorists  should exercise caution.

Road works will take place on Local Road number L-3104-0 in Creevykeel, Cliffoney on Thursday 24th August. Works to last one day. Traffic management and diversions will be in operation.  Motorists should exercise caution.

BALLYMOTE  AREA:

Road works will continue on the R284 at Sooey. Traffic control will be in operation with minimal delays expected.

The installation of a safety barrier will continue on the R296 at Carrownanty, Ballymote. Traffic control will be in place with minimal disruption expected.

TUBBERCURRY  AREA:

Site Investigation works are to continue between Tubbercurry and Annagh Bridge on the R294.  Traffic Management will be in place and minor delays are expected.  Works are expected to last 1 week.

ENNISCRONE  AREA:

Verge trimming will continue on the N59 at Owenbeg, Culleens area.  A Stop/Go system will be in operation.  Minor delays expected.

BALLYSADARE  AREA:

N59 in Ballysadare

Road works will be continuing on the N59 in Ballysadare (between the entrance to Millview Park and the Ballina side of the current 60 kph speed limit zone).

Associated traffic delays should be expected over the course of the contract duration.

Sligo County Council and Gerald Love Contracts will endeavour to minimise the effects of the works where possible and regret any inconvenience which may be caused.

 MINOR WORKS

SLIGO CITY AREA:

A Scaffolding licence has been granted for Ulster Bank.  Works are expected to last 12 weeks.  Some parking spaces will be lost.  Minimal traffic disruption expected.

A Road Opening Licence has been granted for works on Circular Road, just off Pearse Road. Some traffic disruption expected.

Footpath Repairs to take place in Maugheraboy. Minimal traffic disruption expected.

A Scaffolding licence has been granted for Peter Martin Buildings, corner of Teeling Street and Chapel Street. Works are expected to last 4 weeks. Minimal traffic disruption expected.

 SLIGO /STRANDHILL AREA:

Gully cleaning will take place in various locations. Minimal traffic disruption expected.

ENNISCRONE  AREA:

Pothole repair works will continue in the Enniscrone area. Traffic control will be in operation. Minor delays expected.

TUBBERCURRY  AREA:

Pothole repair works will continue in the Tubbercurry area. Traffic control will be in operation but no delays are expected.